FS#29077 — Salle 50B | Room 50B

Attached to Project— Datacenters
Maintenance
Roubaix 4
CLOSED
100%
Resumé: Maintenance de la climatisation
Actions : Remplacement d'un composant
Debut : 04 Janvier 2017 à partir de 13h30 UTC+1
Baies affectées : Salle 50B
Impact : Aucun, le système de climatisation est redondant
Fin estimée : 04 Janvier 2018 14h30 UTC+1


Summary : Air conditioning maintenance
Actions : Replacement of a component
Start : January 04th 2017 at 13h30 UTC+1
Affected Rack : Room 50B
Impact : None, the cooling system is redundant
Finish Time : January 04th 2018 at 14h30 UTC+1
Date:  Thursday, 04 January 2018, 15:54PM
Reason for closing:  
Comment by OVH - Thursday, 04 January 2018, 13:29PM

Nous commençons l'intervention

We begin


Comment by OVH - Thursday, 04 January 2018, 15:53PM

Intervention terminée