FS#33743 — GRA2

Attached to Project— Datacenters
Maintenance
Gravelines
CLOSED
100%
Details
Résumé : Nous allons mettre en service de nouvelles arrivées électrique.
Début : 27/08/18 a partir de 9h00 UTC+2

Impact : Aucun



Summary : We are going to put new power circuits into operation.
Start : Aug, 27th 2018 starting at 9:00AM UTC+2
Impact : None
Date:  Monday, 27 August 2018, 17:36PM
Reason for closing:  Done
Comment by OVH - Monday, 27 August 2018, 17:36PM

Intervention terminée.

Intervention is done.