FS#34012 — P19 - UPS9

Attached to Project— Datacenters
Maintenance
Paris 19
CLOSED
100%
Résumé : Nous allons effectuer la maintenance périodique de l'onduleur
Début : 12 Septembre 2018 à partir de 8h00 UTC+2
Salle affectée : Salle 6
Impact : Aucun
Fin : 12 Septembre 2018 18h00 UTC+2

Summary: We will carry out the periodic maintenance of the UPS.
Start: 12 September 2018 from 8:00AM UTC+2
Assigned room : Salle 6
Impact: None
End: 12 September 2018 6:00PM UTC+2
Date:  Thursday, 13 September 2018, 17:43PM
Reason for closing:  Done