Scheduled Maintenance Report for Network & Infrastructure
Completed
We will replace one tor of this rack.
Switch are active/active so there will be no impact.

Start 2018-11-12 23:00 UTC
End 2018-11-13 05:00 UTC

Reschedule:
Start 2018-11-13 23:00 UTC
End 2018-11-14 05:00 UTC

Update(s):

Date: 2018-11-14 04:33:19 UTC
The network has been stable during the final checks. Redundancy should be restored.

Date: 2018-11-14 03:26:33 UTC
De-isolation has been completed. We will now monitor for stability.

Date: 2018-11-14 02:04:43 UTC
All links migrated over to the new ToR. We will now de-isolate the switch.

Date: 2018-11-14 00:52:23 UTC
Isolation complete. We will now be migrating the devices to the new ToR.

Date: 2018-11-13 23:49:37 UTC
We are currently isolating this device.

Date: 2018-11-13 23:32:47 UTC
We've started the maintenance on this equipment.

Date: 2018-11-13 13:12:27 UTC
Reschedule:
Start 2018-11-13 23:00 UTC
End 2018-11-14 05:00 UTC

Date: 2018-11-13 00:14:35 UTC
We will reschedule this task for an other day due to unforeseen events in the pre-check.

Date: 2018-11-12 23:02:51 UTC
We will be starting the replacement of this device.
Posted Nov 08, 2018 - 11:36 UTC
This scheduled maintenance affected: Infrastructure || SBG (SBG1, SBG3, SBG4).