FS#35518 — CT 1

Attached to Project— Datacenters
Amélioration
Roubaix   → RBX-1
CLOSED
100%
Resumé : Nous allons intervenir sur le système de refroidissement de cette salle.
Debut : 4 Decembre 2018 à partir de 8h00 UTC+1
Baie affectée : CT1
Impact : Aucun
Fin estimée : 5 Decembre 2018 17h00 UTC+1

Summary : We will intervene on the Cooling System of this rack.
Start : 4 Decembre 2018 starting at 8:00AM UTC+1
Affected Rack : CT1
Impact : None
Estimated end: 5 Decembre 2018 5:00PM UTC+1
Date:  Thursday, 06 December 2018, 17:56PM
Reason for closing:  Done
Additional comments about closing:  done
Comment by OVH - Thursday, 06 December 2018, 17:55PM

Intervention complétée

Intervention completed