On Thursday December 6th between 00:00 and 06:00 (UTC-5), we will change the routers present in the Montreal POP by a couple of Nexus N7K and ASR 9K.
All peers currently routed on mtl-1-6k and mtl-2-6k will be moved to the new router.
At the same time, we will add 4*100G of capacity between the BHS DC and the POP in Montreal.
During the intervention, peers will be isolated and moved one by one. Traffic will be re-routed during each move.
Update(s):
Date: 2018-12-06 13:09:07 UTC During the move of mtl-25a/b-ast, we had a problem of MTU with the new infrastructure n7/a9.
We have fix it.
Date: 2018-12-06 11:15:57 UTC The intervention is finished
Date: 2018-12-06 11:15:50 UTC VIDEOTRON is also moved.
Date: 2018-12-06 10:07:34 UTC We are now moving QIX
Date: 2018-12-06 09:02:41 UTC We are now moving TELUS
Date: 2018-12-06 08:44:26 UTC We are now moving LEVEL3
Date: 2018-12-06 08:13:39 UTC We are currently moving BELL peering to the new router.
Date: 2018-12-06 08:13:18 UTC The 4x100G are up.
Date: 2018-12-06 07:07:55 UTC We begin the maintenance.