FS#36150 — SRH4A / SRH4B

Attached to Project— Datacenters
Amélioration
Beauharnois   → BHS-6
CLOSED
100%
Résumé : Nous allons mettre en service les armoires electrique de ces salles.
Début : 10 Janvier 2019 à partir de 7h00 UTC-5
Baies affectée : SRH4A et SRH4B
Impact : Aucun
Durée estimée : 9 heures

Summary: We will put in production the electrical distribution in thoses rooms
Start: January, 10th starting at 7:00 AM UTC-5
Assigned rack: SRH4A and SRH4B
Impact: None
Estimated time: 9 hours
Date:  Friday, 11 January 2019, 11:19AM
Reason for closing:  Done
Comment by OVH - Friday, 11 January 2019, 11:19AM

Intervention terminée.

Intervention done.