FS#36192 — rbx7 - Haute tension

Attached to Project— Datacenters
Maintenance
Roubaix   → RBX-7
CLOSED
100%
Résumé : Nous allons effectuer la mise en service de deux nouveaux transformateurs.
Début : 03 janvier 2019 à partir de 9h00 UTC+1
Baie affectée : rbx7
Impact : Aucun.
Durée estimée : 7h

Summary: We will commission two new transformers.
Start: 3 january 2019 from 9:00am UTC+1
Affected bay: rbx7
Impact: None.
Estimated time: 7h
Date:  Thursday, 03 January 2019, 17:04PM
Reason for closing:  Done
Comment by OVH - Thursday, 03 January 2019, 17:04PM

Les mises en services sont fini

All commissioning were done