OVHcloud Network Status

Current status
Legend
  • Operational
  • Degraded performance
  • Partial Outage
  • Major Outage
  • Under maintenance
GE
Scheduled Maintenance Report for Network & Infrastructure
Completed
Résumé : Nous allons effectuer l'entretien périodique des groupes électrogènes.
Début : 12 Fevrier 2019 à partir de 8h00 UTC+1
Datacentre affectée : RBX1/2/3/4/5/6/7
Impact : Aucun.
Fin estimée : 14 Fevrier 2019 17h00 UTC+1

Summary: We will carry out the periodic maintenance of the generators.
Start: February, 12th of 2019 starting at 8:00 AM UTC+1
Affected datecenter: RBX1/2/3/4/5/6/7
Impact: None.
Estimated end: February, 14th of 2019 5:00 PM UTC+1
Posted Jan 31, 2019 - 21:07 UTC
This scheduled maintenance affected: Infrastructure || RBX (RBX1, RBX2, RBX3, RBX4, RBX5, RBX6, RBX7, RBX8).