FS#45873 — TGBT2 UPS4

Attached to Project— Datacenters
Maintenance
Strasbourg   → SBG-1
Planned
0%
Résumé : Nous allons effectuer une maintenance electrique sur TGBT2 UPS4
Début : 03/août/20 9:00 UTC+2
Datacentre Affecté: SBG1
Impact : Aucun.
Fin estimée : 03/août/20 16:00 UTC+2

Summary: We will perform an electrical maintenance on TGBT2 UPS4.
Start: 03/aug/20 9:00 AM UTC+2
Affected datecenter: SBG1
Impact: None.
Estimated end: 03/aug/20 4:00 PM UTC+2