FS#49707 — N5/N56/N6 ISSU campain

Attached to Project— Network and racks
Maintenance
Entire OVH Network
CLOSED
100%
Details
Description:
An upgrade campaign is launched on all Nexus 5000/5600/6000 of Baremetal aggregator switches.

Impact:
None, upgrade is done trough ISSU (In Services Software Upgrade)

Duration:
Each couples of Nexus 5000/5600/6000 take 1h30-3h00 to be fully upgraded.

Maintenance date:

Date: 29th March.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs-10a/b-n5
bhs1-11a/b-n5
bhs1-12a/b-n5
bhs2-11a/b-n6

Date: 29th March.
Time: 10:00PM - 01:00AM (Paris time) on Gravelines, FR datacenter:
gra1-15a/b-n6
gra1-16a/b-n6
gra1-20a/b-n6
gra1-21a/b-n56

********************************************************************************

Date: 30th March.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs2-15a/b-n6
bhs2-16a/b-n56
bhs2-17a/b-n56
bhs2-18a/b-n56

Date: 30th March.
Time: 10:00PM - 01:00AM (Paris time) on Gravelines, FR datacenter:
gra1-23a/b-n56
gra1-24a/b-n56
gra1-25a/b-n56
gra1-26a/b-n56

********************************************************************************
Date: 31st March.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs2-19a/b-n56
bhs2-20a/b-n56
bhs4-12a/b-n56
sw.192.95.32.248/249-n5

Date: 31st March.
Time: 10:00PM - 01:00AM (Paris time) on Gravelines, FR datacenter:
gra1-27a/b-n56
gra1-30a/b-n56
gra2-17a/b-n56
gra2-21a/b-n56

********************************************************************************

Date: 1st April.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs4-16a/b-n56
bhs4-17a/b-n56
sw.142.4.216.248/249-n5

Date: 1st April.
Time: 10:00PM - 01:00AM (Paris time) on Londres, LON datacenter:
lon1-eri1-11a/b-n56
lon1-eri1-12a/b-n56
lon1-eri1-13a-n56

********************************************************************************
Date:  Friday, 02 April 2021, 01:00AM
Reason for closing:  Done
Comment by OVH - Monday, 29 March 2021, 16:38PM

Attached to https://travaux.ovh.net/?do=details&id=49707


Comment by OVH - Monday, 29 March 2021, 22:02PM

Starting upgrades of "gra1-15a/b-n6", "gra1-16a/b-n6", "gra1-20a/b-n6", "gra1-21a/b-n56". No impact expected


Comment by OVH - Tuesday, 30 March 2021, 03:06AM

the upgrade "gra1-15a/b-n6", "gra1-16a/b-n6", "gra1-20a/b-n6" is completed.
upgrade of "gra1-21a/b-n56" is postponed


Comment by OVH - Tuesday, 30 March 2021, 12:54PM

Date: 30th March.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter

bhs2-16a/b-n56 == Done
bhs2-17a/b-n56 == Done
bhs2-18a/b-n56 == Done


Comment by OVH - Tuesday, 30 March 2021, 22:01PM

I am starting upgrades of gra1-23a/b-n56, gra1-24a/b-n56, gra1-25a/b-n56, gra1-26a/b-n56. No impact is expected. NETCHANGE-1218


Comment by OVH - Wednesday, 31 March 2021, 03:17AM

upgrades of gra1-23a/b-n56, gra1-24a/b-n56, gra1-25a/b-n56 are completed
upgrade of gra1-26a/b-n56 is postponed for later date


Comment by OVH - Wednesday, 31 March 2021, 13:54PM

Date: 31st March.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs2-19a/b-n56 == Done
bhs2-20a/b-n56 == Done
bhs4-12a/b-n56 == Done
sw.192.95.32.248/249-n5 == Done


Comment by OVH - Wednesday, 31 March 2021, 22:00PM

I am starting upgrade of gra1-27a/b-n56, gra1-30a/b-n56, gra2-17a/b-n56, gra2-21a/b-n56. No impact is expected.


Comment by OVH - Thursday, 01 April 2021, 11:05AM

Date: 1st April.
Time: 02:00AM - 06:00AM (Montreal time) on Beauharnois, CA Datacenter
bhs4-16a/b-n56 == Done
bhs4-17a/b-n56 == Done
sw.142.4.216.248/249-n5 == Done


Comment by OVH - Thursday, 01 April 2021, 22:00PM

I am starting upgrades of lon1-eri1-11a/b-n56, lon1-eri1-12a/b-n56, lon1-eri1-13a/b-n56. No impact.


Comment by OVH - Friday, 02 April 2021, 01:00AM

The upgrades of lon1-eri1-11a/b-n56, lon1-eri1-12a/b-n56, lon1-eri1-13a/b-n56are successfully completed.