Resumé : Nous allons effectuer la maintenance sur la partie électrique de cette rangée.
Debut: 14/Apr/21 10:00 UTC+2
Fin : 14/Apr/21 14:00 UTC+2
Salle affectée: W14
Impact : Aucun
Summary : We will perform the maintenance on the electrical way of this row.
Start: 14/Apr/21 10:00 AM UTC+2
End : 14/Apr/21 2:00 PM UTC+2
Affected Room: W14
Impact : None
Date: Wednesday, 14 April 2021, 21:58PMDebut: 14/Apr/21 10:00 UTC+2
Fin : 14/Apr/21 14:00 UTC+2
Salle affectée: W14
Impact : Aucun
Summary : We will perform the maintenance on the electrical way of this row.
Start: 14/Apr/21 10:00 AM UTC+2
End : 14/Apr/21 2:00 PM UTC+2
Affected Room: W14
Impact : None
Reason for closing: Done
Additional comments about closing: done
Nous commençons l'intervention
We begin the intervention
Intervention complétée.