Operator maintenance is planned for ADSL and VDSL Internet access on Orange collect.
It will be carried out by zone and by batch in a period from August to November 2021.
Depending on the access, three cases may arise:
+ For the majority of accesses (97.1%), the action carried out is a change in the software configuration of the operator's network equipment.
The impact is an interruption of a few seconds.
You will be notified 5 days and then 24 hours before the maintenance is initiated, which will be carried out within half a day.
+ For a small part of the accesses (2.7%), the maintenance will also require an intervention in the NRA.
The impact is an indicative outage time of 10 minutes.
You will be notified 5 days and then 24 hours before the maintenance is initiated, which will take place within 3 days.
+ For a very small proportion of accesses (0.2%), maintenance will not be possible within the defined period and will have to be rescheduled later.
We will indicate the overall progress of the maintenance in this task.
Friday, 13 August 2021, 14:23PM
Lot 1 : +0.3% des migration pour couvrir toute les zones de France: initié le 2021-07-28 , migration à partir du 2 Aout
Lot 2 : +1.5% des migration. Les migrations sont dans la zone Aquitaine : initié le 2021-08-04 , migration à partir du 9 Aout
Lot 3 : +3.7% des migration. Les migrations sont dans la zone Aquitaine : initié le 2021-08-11 , migration à partir du 16 Aout
Total des migrations lancées 5,5%
-----------------------
Batch 1: + 0.3% of migration to cover all areas of France: initiated on 2021-07-28 , migration from August 2
Batch 2: + 1.5% of migration. Migrations are in the Aquitaine zone: initiated on 2021-08-04 , migration from August 9
Batch 3: + 3.7% of migration. Migrations are in the Aquitaine zone: initiated on 2021-08-11 , migration from August 16
Total migration initiated 5.5%
Thursday, 19 August 2021, 14:46PM
Lot 4 : +4.2% des migration. Les migrations sont dans la zone Aquitaine et Auvergne : initié le 18 Aout , migration à partir du 23 Aout.
Total des migrations lancées 9,7%
-------------------
Batch 4 : +4.2% of migration. Migrations are in the Aquitaine and Auvergne zone : initiated on 2021-08-18 , migration from August 23.
Total migration initiated 9.7%.
Thursday, 26 August 2021, 09:56AM
Lot 5 : +4.1% des migration. Les migrations sont dans la zone Bretagne : initié le 26 Aout , migration à partir de 31 Aout
Total des migrations lancées 13,8%
-------------------------------------------------
Batch 5 : +4.1% of the migration. The migrations are in the Bretagne area : initiated on August 26, migration from August 31
Total migration initiated 13,8%
Thursday, 02 September 2021, 12:08PM
Lot 6 : +3.8% des migration. Les migrations sont dans la zone Bretagne : initié le 2 Septembre, migration à partir de 7 Septembre
Total des migrations lancées 17,6%
------------------
Batch 6 : +3.8% of the migration. The migrations are in the Bretagne area : initiated on September 2, migration from September 7
Total of initiated migrations 17,6%
Thursday, 09 September 2021, 11:06AM
Lot 7 : +5.6% des migration. Les migrations sont dans la zone Picardie et Bourgogne Franche Comté : initié le 09 Septembre, migration à partir de 17 Septembre
Total 23,2%
------------------------------------------------------------------------
Lot 7: + 5.6% of migration. The migrations are in the Picardy and Bourgogne Franche Comté zone: initiated on September 09, migration from September 17
Total 23.2%
Thursday, 16 September 2021, 15:25PM
Lot 8 : +7.4% des migrations. Les migrations sont dans la zone Centre : initié le 16 Septembre, migration à partir de 23 Septembre
Total 30,6%
---------------------------------
Lot 8: + 7.4% of migrations. The migrations are in the Center zone: initiated on September 16, migration from September 23
Total 30.6%
Thursday, 23 September 2021, 11:41AM
Lot 9 : +6.7% des migration. Les migrations sont dans la zone Provence : initié le 23 Septembre, migration à partir de 30 Septembre
------------------------------------------
Lot 9 : +6.7% of the migration. Migrations are in the Provence area : initiated on September 23, migration from September 30
Thursday, 30 September 2021, 11:24AM
Lot 10 : +7.5% des migration. Les migrations sont dans la zone Limousin Poitou Charente : initié le 30 Septembre, migration à partir de 5 Octobre
-----------------
Bacth 10 : +7.5% of the migration. Migrations are in the Limousin Poitou-Charentes area : initiated on September 30, migration from October 5
Total 42,8%
Thursday, 07 October 2021, 15:34PM
Lot 11 : +7.5% des migration. Les migrations sont dans la zone Pays de Loire : initié le 7 Octobre, migration à partir de 12 Octobre
------------
Bacth 11 : +7.5% of the migration. Migrations are in the Pays de Loire area : initiated on October 7, migration from October 12
Total 50,3%
Thursday, 21 October 2021, 13:56PM
Lot 12 : +8.9% des migration. Les migrations sont dans les zones Midi Pyrénées et Haute Normandie : initié le 21 Octobre, migration à partir de 26 Octobre
--------
Batch 12: + 8.9% of migration. The migrations are in the Midi Pyrénées and Haute Normandie areas: initiated on October 21, migration from October 26
Total 59,2%
Thursday, 04 November 2021, 09:55AM
Lot 13 : +10.4% des migration. Les migrations sont dans les zones Alsace, Lorraine et Alpes Sud : initié le 04 Novembre, migration à partir de 9 Novembre
-------
Batch 13: + 10.4% of migration. The migrations are in the Alsace, Lorraine and Alpes Sud areas: initiated on November 4, migration from November 9
Total 69,6%
Thursday, 18 November 2021, 10:44AM
Lot 14 : +11.1% des migration. Les migrations sont dans les zones Rhône, Nord Pas de Calais et Basse Normandie : initié le 18 Novembre, migration à partir de 23 Novembre
-------
Batch 14: +11.1% of migration. The migrations are in the Rhône, Nord Pas de Calais and Basse Normandie areas: initiated on November 18, migration from November 23
Posted Nov 22, 2021 - 15:22 UTC