Core DC - Update Cisco concentrators campain
Scheduled Maintenance Report for Network & Infrastructure
Completed
Description

An upgrade campaign is launched on all DC core switches for reliability and manufacturer support. No Service Impact is expected.


Maintenance date: 8th November 2021, 8:00 - 12:00 (UTC Time) in Beauharnois, CAN datacenter:
bhs7-c7/c8-n93
bhs7-c11/c12-n93

Maintenance date: 8th November 2021, 21:00 - 9th November 2021, 02:00 (UTC Time) in Limburg, FRA datacenter:
fra1-lim1-c7/c8-n93

Maintenance date: 8th November 2021, 21:00 - 9th November 2021, 02:00 (UTC Time) in Roubaix, FR datacenter
rbx7-c7/c8-n93
rbx4-c5/c6-n92




Update(s):

Date: 2021-11-08 23:48:47 UTC
rbx4-c5/c6-n92 have been successfully upgraded

Date: 2021-11-08 22:42:12 UTC
Starting the upgrade of rbx4-c5/c6-n92 now.

Date: 2021-11-08 22:27:03 UTC
fra1-lim1-c8-n93, rbx7-c8-n93 successfully upgraded !

Date: 2021-11-08 22:06:55 UTC
Starting the upgrade of fra1-lim1-c8-n93, rbx7-c8-n93

Date: 2021-11-08 22:06:33 UTC
fra1-lim1-c7-n93, rbx7-c7-n93 upgraded


Date: 2021-11-08 21:09:33 UTC
Starting the software upgrade of Core Switches - fra1-lim1-c7-n93, rbx7-c7-n93


Date: 2021-11-08 10:17:00 UTC
bhs7-c7/c8-n93 and bhs7-c11/c12-n93 has been successfully upgraded.



Date: 2021-11-08 08:35:55 UTC
Hi,
We will start software upgrade of :
bhs7-c7/c8-n93
bhs7-c11/c12-n93
Posted Oct 26, 2021 - 14:24 UTC