Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
Gblx va changer le routeur sur lequel Ovh est connecté.
New Start Date/Time of Event:
2005-11-18 23:00:00-GMT
New End Date/Time of Event:
2005-11-19 05:00:00-GMT
Reason for Work:
Replacement of hardware on router.
Impact to Global Crossing Network:
Global Crossing will be performing a maintenance on ar2.cdg2 to resolve an
on going problem that is a result of a vendor's manufacturing defect. The
hardware swap is anticipated to lead to final resolution of this issue.
Additionally, if further problems are seen we will perform a complete
hardware swap on the router in question. Due the confidence from the
vendor that root cause has been identified we will only perform a complete
hardware swap only if necessary. The expected duration is 30 minutes, but could be extended by 2 hours if problems arise.