In order to improve the OVHcloud network, we are going to install our new Backbone infrastructure in Paris and we are going to start with our TH2 POP.
It is going to be done in 3 steps in order to minimize the risks. Here is the planning of the migration:
> 27/07 - 22:00 (CEST) - First step by putting in production the first router
> 28/07 - 22:00 (CEST) - Second step by migrating the BGP peers to the brand new routers
> 29/07 - 22:00 (CEST) - Third step by migrating services to the new infrastructure, such as OVHcloud Connect, xDSL
No impact is expected.
Update(s):
Date: 2020-07-30 03:17:08 UTC We had an issue on our xDSL infrastructure. We have done a rollback in order to understand what happened.
Date: 2020-07-30 02:35:34 UTC Done. We are verifying the entire infrastructure.
Date: 2020-07-30 01:01:37 UTC Done. We are verifying the entire infrastructure.
Date: 2020-07-29 23:29:56 UTC Done. We continue with xDSL infrastructure.
Date: 2020-07-29 21:14:58 UTC Done. We continue with OCC/vRack Connect.
Date: 2020-07-29 21:04:22 UTC We are going to start the maintenance. We start with the VOIP. No impact is expected.
Date: 2020-07-29 01:32:32 UTC Done. We are going to verify the entire infrastructure.
Date: 2020-07-28 21:05:37 UTC We are going to start the maintenance with the BGP Peers.